Erection of 23 megawatt facility. Our scope included erection of boiler, setting of turbine, generator, surface condenser, and assembly of step grate stoker. Shown is setting of 80'-0" tall rear wall.
|  |
One of four (4) German designed boilers erected by our field crews. 60" diameter steam drum and twin 36" diameter mud drums are shown on structural supports prior to tube installation.
|  |
Installation of 25,000 #/hr. package boiler. Scope included setting of boiler, economizer, stack and power piping.
|  |
Shown is 400,000 #/hr. field erected boiler for steel mill service. Unit is designed to burn blast furnace waste gas.
|  |
|